Skip to site content
Wastewater Treatment

Phasing Oxidation Ditch & Clarifier Rehabilitation to Ensure Continued Operations

Problem

The Fishcreek Water Reclamation Facility contains two parallel treatment processes: an oxidation ditch (OD) maintained in regular service and rotating biological contactors (RBC) which have been disused since the OD was constructed circa 1998. Each process is individually rated for an average daily flow of four million gallons. Rehabilitating the OD and its final clarifiers requires careful phasing to first restore the RBC clarifiers and supporting elements to operating condition to ensure continued treatment when work on the OD is performed.

 

Solution

CTI was selected to design process, mechanical, and electrical improvements focusing on the OD treatment train. Improvements include restoration of the RBC clarifiers, complete mechanical and electrical overhaul of a sludge pumping station and force main, modifications to effluent and sludge diversion structures, and construction of a gravity bypass from the OD to the RBC clarifiers.

 

Project Elements

  • Hydrologic and hydraulic analysis
  • Complete mechanical and electrical overhaul of a sludge pumping station and force main
  • Modifications to effluent and sludge diversion structures
  • Construction of a gravity bypass from the OD to the RBC clarifiers

 

CTI Services

  • Preliminary Engineering
  • Process Design, Engineering, Plan & Bid Document Generation
  • Permitting and Funding Assistance
  • Bid Support and Construction Oversight
  • Planning and Construction Phasing
See All Projects
Client

Summit County Department of Sanitary Sewer Services

Project Cost

$3.75M (Est.)

Funding

Local

CTI Personnel on project

Rick Reed, PE

Zak Kaczor, PE

Other Wastewater Treatment Projects

Practical Innovation By Design

CTI Engineers has been providing practical, but innovative, solutions to engineering challenges using nature’s inspiration to enhance and protect the natural world since 1991. 

About Us