Sewer Extension to Shellmound Business Park

Shellmound Sewers 2

PROJECT SUMMARY

The Town of Jasper committed to provide public sewer service in the area of the I 24/Hwy 41/Hwy 27 interchange. This not only accommodated the travel center but spurred the construction of additional businesses in the area.

PROJECT ELEMENTS
  • Contract 1: Line Work – Approximately 19,000 LF of 6-inch PVC sewer force main along county roads and state highways, including cased and uncased highway crossings, directional bore of river, and appurtenances.
  • Contract 2: Pump Stations – 250-gpm, duplex submersible sewage pump station and underground, 300-gpm, duplex, water booster pump station, electrical and site work.
SERVICES PROVIDED BY CTI PERSONNEL
  • Preliminary engineering report
  • Design services
  • Bidding phase services
  • Construction phase services
  • Resident project representation
  • Surveys
  • Easement documents
  • Permitting assistance and SWPPP
  • Subsurface exploration
  • RD environmental report amendment and archaeological survey
Project Description

When a major travel center was selecting the site for a $7 million facility, the provision of sewers was a major factor in its decision.

Project Details
  • Client: Town of Jasper, Tenn.