Morris Estates Drainage

Morris Estates

PROJECT SUMMARY

CTI designed a storm sewer system of pipelines, inlets, spillways, curbs, and culverts to properly channel storm water flows to eliminate flooding of several basements on Foster Drive. The design also added four box culverts under each major road in the subdivision that the main drain ditch crossed.

PROJECT ELEMENTS

  • 800 LF of storm pipes, inlets, spillways, and curb
  • 10x3 Precast Box Culvert under Stanley Drive
  • 10x4 Precast Box Culvert under Ruth Lane
  • 12x4 Precast Box Culvert under Woodie Drive
  • Dual 8x4 Precast Box Culvert under Foster Drive
  • Channel bank stabilization
  • Site restoration and road repair

SERVICES PROVIDED BY CTI PERSONNEL

  • Preliminary engineering report
  • Hydrologic and hydraulic modeling
  • Easement assistance
  • Permitting
  • Planning, design, and CAD drawings
  • Construction phase services
  • Resident project representation
Project Description

Older portions of this well-established subdivision were constructed without the benefit of a complete storm water system. Runoff into these areas increased as a result of paving and grading in newer parts of the development. In the older areas, the streets served as drainageways, eventually overflowing into yards and homes.

Project Details
  • Client: Catoosa County, Ga.